Zettabyte and Chief Telecom Transform Taiwan Data Center into GB300 Ready AI Hub

Legacy air-cooled Data Center transformed into GPU-ready AI Data Center in record time and cost.

the Project

Enabling Sovereign AI Data Centers

Zettabyte and Chief Telecom transformed a legacy data center into a liquid cooled GPU enabled AI Data Center in just 45 days, half the usual timeline.

"This milestone showcases how Zettabyte's technology accelerates the transition from legacy to next-generation AI data centers," said Kenneth Tai, Chairman of Zettabyte.

"In just 45 days, we turned Chief's facility into a GB300-ready hub. This is a blueprint for how the world's data centers can adapt to the AI era, fast, efficiently, and sustainably."

"At Chief Telecom, we are committed to pioneering the future of AI services in Taiwan and beyond," added Johnny Liu, CEO of Chief Telecom. "Partnering with Zettabyte allowed us to transform our infrastructure at unprecedented speed, ensuring our customers can access the most advanced, power-dense AI platforms available today."

This pilot project marks the first milestone for Zettabyte TITAN, the company's flagship initiative to “redefine next-generation AI infrastructure.”

TITAN was launched in September of 2025. The initiative is designed to support the accelerating demands of intense workloads, and aims to accelerate Zettabyte's data center supply chain buildout in Taiwan.

Specification

Facility

Building infromration

Land Space

46,000 ft2

Total Floor Space

160,000 ft2

Total Floors

7 above ground, 2 underground

Floor Height

6 Meter

Building Structure

RC

Floor Loading

2,000 kg/m2   (19.61 kN/m2)

Lift Load Capacity

– 3,500 kg x1 (Door dimension: H: 2.5M W:2.6M)
– 2,500 kg x1 (Door dimension: H: 2.4M W:1.9M)

Building Design

Intelligent building; Green building

Point of Fiber Entry

4

Seismic Isolation Design

0.41G seismic coefficient, capable of withstanding earthquakes of magnitude 7 or above

Floor Protection Design

Site elevation raised by 1.2 meters (based in Taipei City's 200-year flood level benchmark)

Infrastructure

IDC information

Power Supply

- Total capacity: 20 MW
- Dual Taipower substations with 22.8 kV high-voltage feed

Water Storage

Supports 72 hours of full-load operation

Generator / Transformer

- N+2 redundancy design
- Supports 24 hours of full-load operation

UPS

- 2N redundancy design
- Battery backup supports 15 minutes of full load operation

Cooling System

- Dual-loop water piping
- High-efficiency centrifugal chiller
- Enclosed cold aisle cabinet design

Fire Protection System

- VESDA early smoke detection system
- Environmentally friendly gas fire extinguisher (Novec1230)

HPC Support

Flexible power density design

24x7 Operational Support

- Network Operations Center (NOC)
- Mechanical & electrical facilities maintenance (M&E)
- Security management
1st
Air to liquid cooled upgrade in Taiwan
100+kW
Power per rack enabled
GB300
GPU ready data hall